Phase I
Tower
|
Expected Possession
|
Current Status
|
A-1P
|
Late 2014
|
Structure Completed,Finishing
Work in progress
|
A-1Q
|
Late 2014
|
Structure Completed,Finishing
Work in progress
|
A-1R
|
Late 2014
|
Structure Completed,Finishing
Work in progress
|
A-4
|
Late 2014
|
Structure Completed,Finishing
Work in progress
|
B-4
|
Late 2014
|
Structure Completed,Finishing
Work in progress
|
B-5
|
Late 2014
|
Structure Completed,Finishing
Work in progress
|
B-6
|
Late 2014
|
Structure Completed,Finishing
Work in progress
|
C-4
|
Late 2014
|
Structure Completed,Finishing
Work in progress
|
C-5
|
Late 2014
|
Structure Completed,Finishing
Work in progress
|
D-3
|
Late 2014
|
Structure Completed,Finishing
Work in progress
|
B-3
|
Early 2015
|
19th floor slab work in
progress
|
D-2
|
Early 2015
|
Structure Completed,Finishing
Work in progress
|
D-4
|
Late 2014
|
Structure Completed,Finishing
Work in progress
|
E-4
|
Early 2015
|
Structure Completed,Finishing
Work in progress
|
E-5
|
Late 2014
|
Structure Completed,Finishing
Work in progress
|
Phase II
Tower
|
Possession Date
|
Current Status
|
B-1
|
Early 2015
|
20th floor slab work in
progress
|
B-2
|
Early 2015
|
20th floor slab work in
progress
|
A-2
|
Mid 2015
|
17th floor slab work in
progress
|
A-2X
|
Mid 2015
|
17th floor slab work in
progress
|
A-2Y
|
Mid 2015
|
18th floor slab work in
progress
|
A-2Z
|
Mid 2015
|
16th floor slab work in
progress
|
A-3
|
Mid 2015
|
16th floor slab work in progress
|
A-3M
|
Mid 2015
|
16th floor slab work in
progress
|
A-3N
|
Mid 2015
|
16th floor slab work in
progress
|
B-11
|
Mid 2015
|
17th floor slab work in
progress
|
B-12
|
Mid 2015
|
17th floor slab work in
progress
|
B-12A
|
Mid 2015
|
15th floor slab work in
progress
|
B-14
|
Mid 2015
|
17th floor slab work in
progress
|
B-15
|
Mid 2015
|
20th floor slab work in
progress
|
B-16
|
Mid 2015
|
20th floor slab work in
progress
|
B-17
|
Mid 2015
|
Structure Completed,Finishing
Work in progress
|
B-8
|
Mid 2015
|
20th floor slab work in
progress
|
B-9
|
Mid 2015
|
Structure Completed,Finishing
Work in progress
|
B-10
|
Mid 2015
|
Structure Completed,Finishing
Work in progress
|
B-18
|
Mid 2015
|
17th floor slab work in
progress
|
C-2
|
Mid 2015
|
13th floor slab work in
progress
|
C-3
|
Mid 2015
|
14th floor slab work in
progress
|
E-1
|
Late 2015
|
18th floor slab work in
progress
|
F-1
|
Late 2015
|
Structure Completed,Finishing
Work in progress
|
G-1
|
Late 2015
|
Structure Completed,Finishing
Work in progress
|
Phase III
Tower
|
Possession Date
|
Current Status
|
D-5
|
Mid 2015
|
Structure Completed,Finishing
Work in progress
|
E-6
|
Mid 2015
|
Structure Completed,Finishing
Work in progress
|
E-7
|
Mid 2015
|
Structure Completed,Finishing
Work in progress
|
F-7
|
Early 2015
|
Structure Completed,Finishing
Work in progress
|
F-5
|
Early 2015
|
Structure Completed,Finishing
Work in progress
|
G-5
|
Early 2015
|
Structure Completed,Finishing
Work in progress
|
N-1
|
Mid 2015
|
Structure Completed,Finishing
Work in progress
|
N-2
|
Mid 2015
|
19th floor slab work in
progress
|
N-3
|
Mid 2015
|
19th floor slab work in
progress
|
S-1
|
Early 2015
|
Structure Completed,Finishing
Work in progress
|
S-2
|
Early 2015
|
Structure Completed,Finishing
Work in progress
|
S-3
|
Early 2015
|
Structure Completed,Finishing
Work in progress
|
S-3A
|
Early 2015
|
Structure Completed,Finishing
Work in progress
|
S-3B
|
Early 2015
|
Structure Completed,Finishing
Work in progress
|
C-6
|
Late 2015
|
18th floor slab work in
progress
|
K-1
|
Late 2015
|
12th floor slab work in
progress
|
K-2
|
Late 2015
|
13th floor slab work in
progress
|
J
|
Late 2015
|
17th floor slab work in
progress
|